Herefordshire Council has promised a raft of measures to make up for the prolonged disruption caused by ongoing improvements to Leominster town centre.
Last month it wrote to businesses affected in the town explaining that “difficulties with drainage and the sourcing of materials” meant the extensive programme of work would not now be completed until late November.
It now aims to have the work to the High Street, Corn Street, Victoria Street and Iron Cross finished by the end of September as planned, with only the work in Corn Square taking the extra two months.
RELATED NEWS:
- Leominster's Etnam Street car park offers free parking
- New site for Leominster Food Fayre confirmed
- Flat plan confirmed for long-empty Leominster shop
The council is already offering two hours’ free parking each day in nearby Etnam Street car park for the duration of the work.
What are your thoughts?
You can send a letter to the editor to have your say by clicking here.
Letters should not exceed 250 words and local issues take precedence.
It is also making £2,500 available to promote events and festivals in the town, working with the town council and local businesses, and is supporting events such as the town’s Food Fayre which have been displaced by the work.
The county council says it is also working with contractors to “minimising disruption” caused by signs and safety barriers around the works, following concern expressed by businesses and residents.
Meanwhile Herefordshire County Business Improvement District has separately committed to providing up to £10,000 in marketing to support Leominster’s businesses.
Comments: Our rules
We want our comments to be a lively and valuable part of our community - a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
Read the rules hereLast Updated:
Report this comment Cancel